Wednesday, June 30, 2010. NOTICE OF BLASTING ACTIVITY. This is to notify interested parties that blasting activity will take place at:. Hot Sulphur Springs Water Tank. Hot Sulphur Springs, Colorado. Blasting will commence on: Monday, July 5, 2010. Blasting will continue through: Friday, July 16,2009. Prior to each detonation there will be a five-minute and then a one-minute pre-blast warning signal. After each blast there will be an all-clear signal. If you have any questions, please contact:. By using m...
hotsulphurconstructioninfo.blogspot.com
HSW Construction Information: November 2009
http://hotsulphurconstructioninfo.blogspot.com/2009_11_01_archive.html
Friday, November 13, 2009. Invitation to Bid for Storage Tank Solar Reservoir Circulator. An Invitation to Bid. Is being advertised in the MP Times and Sky Hi Daily News on November 12 and 13. The announcement gives information about bidding for the Hot Sulphur Springs Solar Reservoir Circulator. Bids are due at the Hot Sulphur Springs Town Hall on November 23, 2009 at 11 am. To receive an email every time this page is updated click here. Invitation to Bid for Storage Tank Solar Reservoir.
hotsulphurconstructioninfo.blogspot.com
HSW Construction Information: April 2010
http://hotsulphurconstructioninfo.blogspot.com/2010_04_01_archive.html
Monday, April 26, 2010. First Concrete Pour for our New Clear Well! We completed the excavation and poured the first slab for our new clear well, which will be the tank underneath the new water treatment plant. The 20 X 10 foot slab in the photo is actually the floor for a sump. Weather permitting, we will begin to pour the walls. Monday, April 12, 2010. The Garney crew is here in full force and will be working Monday-Thursday. Beginning Monday April 12, they will be excavating the clear well area wh...
hotsulphurconstructioninfo.blogspot.com
HSW Construction Information: July 2010
http://hotsulphurconstructioninfo.blogspot.com/2010_07_01_archive.html
Monday, July 26, 2010. Yenter Completes Blasting at Tank Site. Yenter has completed blasting and Garney has hauled most of the excavated material off site, leaving this nice rock bench almost ready for forming our tank foundation. Lots of hard work is paying off! Monday, July 19, 2010. New Water Filter Arrives! The Town of Hot Sulphur Springs is the proud new owner of a state-of-the-art Siemens water filter! This photo shows the tight fit through the garage-style door (careful now!
hotsulphurconstructioninfo.blogspot.com
HSW Construction Information: February 2010
http://hotsulphurconstructioninfo.blogspot.com/2010_02_01_archive.html
Saturday, February 6, 2010. Project Timeline - Feb 2010. The construction and administration teams have developed this Project Timeline for February 2010. Outdoor construction will begin soon at the water tank site. We will update this web page with more information as it is available. Wednesday, February 3, 2010. Stimulus team is using our scheduled winter break from construction to focus on enhancing project communications and developing final construction details. Curt Thompson, George Cicoff. Hot Sul...
hotsulphurconstructioninfo.blogspot.com
HSW Construction Information: Ribbon Cutting Ceremony - Nov. 13 at 11:00
http://hotsulphurconstructioninfo.blogspot.com/2010/10/ribbon-cutting-ceremony-nov-13-at-1100.html
Friday, October 15, 2010. Ribbon Cutting Ceremony - Nov. 13 at 11:00. The official Ribbon Cutting Ceremony for the Hot Sulphur Springs Water Project will be held on Saturday, November 13 at 11 am at the new Water Treatment Plant at 400 Maple. Please join with us to celebrate this successful and much-needed project! To receive an email every time this page is updated click here. And send us a note with your email address and the name of this page "Construction". Water Tank is Completed.
hotsulphurconstructioninfo.blogspot.com
HSW Construction Information: June 2011
http://hotsulphurconstructioninfo.blogspot.com/2011_06_01_archive.html
Friday, June 17, 2011. We Passed Final Inspection. CDPHE Engineer Andy Poirot has approved our final inspection, closing out this ARRA project on time and within budget. At our peak we had 18 people working on this project, including the Garney Construction team that rented rooms from the Stagecoach Inn for the season, giving the town an additional shot in the arm during some difficult economic times. Program Manager, Geoff Elliott and His Team.
hotsulphurconstructioninfo.blogspot.com
HSW Construction Information: New Water Treatment Filter Operational
http://hotsulphurconstructioninfo.blogspot.com/2010/09/new-water-treatment-filter-operational.html
Wednesday, September 29, 2010. New Water Treatment Filter Operational. The new water filter has now been running for a week and is ready to go on line as soon as final tests are complete. Photos show our water plant operators Jim Kleeman and Jack Zielinski test driving the new system to optimize residual chlorine content. Great to see the sink flowing with good clean water! To receive an email every time this page is updated click here. New Water Treatment Filter Operational.
hotsulphurconstructioninfo.blogspot.com
HSW Construction Information: March 2010
http://hotsulphurconstructioninfo.blogspot.com/2010_03_01_archive.html
Wednesday, March 24, 2010. Construction begins at Both Sites. Construction for 2010 has begun at both the water treatment plant site and the water tank site. Work will be focused near the water treatment plant, until the water tank site dries out. Tuesday, March 9, 2010. Construction to start March 15, 2010. To receive an email every time this page is updated click here. And send us a note with your email address and the name of this page "Construction". Construction begins at Both Sites.