knostropsludge.blogspot.com
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME: July 2007
http://knostropsludge.blogspot.com/2007_07_01_archive.html
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME. Friday, 20 July 2007. July Developments Part II. The concrete pours in the 2 day area were completed on July 20th involving Scarlet, one of the B&V subcontrators for this project. In the 21 day area, design of the connections was reconsidered with a manhole incorporated. Complex existing services below the ground were also found, presenting a temporary logistical nightmare which was later dealt with. Particular focus was given to meeting programme timescales. Subsc...
naburnsludge.blogspot.com
NABURN WWTW SLUDGE MANAGEMENT SCHEME: May 2007
http://naburnsludge.blogspot.com/2007_05_01_archive.html
NABURN WWTW SLUDGE MANAGEMENT SCHEME. Friday, 18 May 2007. Naburn WwTW Social Event. A social event was held in the city of York on 17-05-07 in order to build and bond the team to try and guarantee the success and quality of the project. Tuesday, 15 May 2007. The excavations and cofferdam installation for FST5 and 6 Hopper are working to the existing method statement. Pipe installation under the FST tanks began and there is an option to have more focus on ths dependent upon the coming ground conditions.
naburnsludge.blogspot.com
NABURN WWTW SLUDGE MANAGEMENT SCHEME: June - July Developments
http://naburnsludge.blogspot.com/2007/10/post-6.html
NABURN WWTW SLUDGE MANAGEMENT SCHEME. Tuesday, 31 July 2007. June - July Developments. Information limited at this time. Subscribe to: Post Comments (Atom). June - July Developments. View my complete profile. How often would you like to see this blog updated?
naburnsludge.blogspot.com
NABURN WWTW SLUDGE MANAGEMENT SCHEME: August Update
http://naburnsludge.blogspot.com/2007/10/post-8.html
NABURN WWTW SLUDGE MANAGEMENT SCHEME. Friday, 17 August 2007. In line with the focus upon safety at all the B&V sites, Naburns pedestrian routes were were newly designed and completed as well as Charles Arrowsmith from B&V Health and Safety giving a safety talk relating to safe lifting with excavators. Subscribe to: Post Comments (Atom). View my complete profile. How often would you like to see this blog updated?
naburnsludge.blogspot.com
NABURN WWTW SLUDGE MANAGEMENT SCHEME: April 2007
http://naburnsludge.blogspot.com/2007_04_01_archive.html
NABURN WWTW SLUDGE MANAGEMENT SCHEME. Sunday, 29 April 2007. Steel for the selector tank has been identified with most parts having already arrived for work to commence on 30-04-07. Wednesday, 25 April 2007. Excavations have been ongoing with an increase in staff numbers to speed up the works. Tool box talks have also had a focus with topics including:. Ladders and hand tools. The fencing has also been improved with the traffic management plan in place. Subscribe to: Posts (Atom). View my complete profile.
knostropsludge.blogspot.com
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME: October 2007
http://knostropsludge.blogspot.com/2007_10_01_archive.html
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME. Wednesday, 31 October 2007. 21 Day Area Concrete Pouring. The base for tank 4 was poured on 26-10-07 and took until 3am with staff members enthusiasm highly commendable. The rebar for tank 3 was completed on the same day with the concrete to be poured on 01-11-07, completing all the concreting for that area. I am where I am because I believe in all possibilities". Friday, 19 October 2007. 2 Day Tank Area: Roof Lifted into Place. Act as if it were impossible to fail".
knostropsludge.blogspot.com
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME: June 2007
http://knostropsludge.blogspot.com/2007_06_01_archive.html
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME. Tuesday, 26 June 2007. Use of Recycled Imported Material. Use of recycled imported material and reuse of in situ excavated material:. Knostrop is the main Waste Water treatment Works serving the city of Leeds and the scheme is valued at circa £10m and programmed for completion over an 18 month period ending June 2008. A decision was made by the site management team to bring a licensed mobile concrete crusher on to site to crush the discovered demolition material...
knostropsludge.blogspot.com
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME: Construction Progress: March
http://knostropsludge.blogspot.com/2008/03/construction-progress-march.html
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME. Monday, 31 March 2008. TK58100 crack injection complete. Re-filling for water test ongoing. Cross site odour duct bases complete. TK62400 concrete repairs completed by A Consult. All ring beams are concreted. MCC21-2 is excavated and constructed, base complete and awaiting kiosk. Odour control unit base commenced and ongoing. PC pump base excavate and construct. Tank No.2- Concrete repairs to the existing tank complete in accordance with PMI.
knostropsludge.blogspot.com
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME: Construction Operations
http://knostropsludge.blogspot.com/2008/03/construction-operations.html
KNOSTROP WWTW SLUDGE MANAGEMENT SCHEME. Monday, 10 March 2008. 21 Day Tank Area: Panels and roof for tank 4 have been erected as well as pouring for ring beam. 70% of access steelwork erected. Blinding and trench base poured for MCC. Excavation and underslab ducts for pump slab and odour control slab. 2 Day Tank Area: Electrical above ground feed pipework and pipework around pumps, odour control duct, valves in manholes installed. Subscribe to: Post Comments (Atom). View my complete profile.