NABURN WWTW SLUDGE MANAGEMENT SCHEME. Friday, 18 May 2007. Naburn WwTW Social Event. A social event was held in the city of York on 17-05-07 in order to build and bond the team to try and guarantee the success and quality of the project. Tuesday, 15 May 2007. The excavations and cofferdam installation for FST5 and 6 Hopper are working to the existing method statement. Pipe installation under the FST tanks began and there is an option to have more focus on ths dependent upon the coming ground conditions.
naburnsludge.blogspot.com
NABURN WWTW SLUDGE MANAGEMENT SCHEME: June - July Developments
http://naburnsludge.blogspot.com/2007/10/post-6.html
NABURN WWTW SLUDGE MANAGEMENT SCHEME. Tuesday, 31 July 2007. June - July Developments. Information limited at this time. Subscribe to: Post Comments (Atom). June - July Developments. View my complete profile. How often would you like to see this blog updated?
naburnsludge.blogspot.com
NABURN WWTW SLUDGE MANAGEMENT SCHEME: August Update
http://naburnsludge.blogspot.com/2007/10/post-8.html
NABURN WWTW SLUDGE MANAGEMENT SCHEME. Friday, 17 August 2007. In line with the focus upon safety at all the B&V sites, Naburns pedestrian routes were were newly designed and completed as well as Charles Arrowsmith from B&V Health and Safety giving a safety talk relating to safe lifting with excavators. Subscribe to: Post Comments (Atom). View my complete profile. How often would you like to see this blog updated?
hullsludge.blogspot.com
HULL WWTW SLUDGE MANAGEMENT SCHEME: November 2007
http://hullsludge.blogspot.com/2007_11_01_archive.html
HULL WWTW SLUDGE MANAGEMENT SCHEME. Thursday, 1 November 2007. Over the next 5 weeks the new coarse screens are to be installed along with the associated screw conveyors and access structures. The temporary screens installed in the lamellas are to be removed this week. After alteration and refurbishment at Adams they will be returned to site and installed in the existing FFT chambers to screen FFT flows. Subscribe to: Posts (Atom). Health and Safety Executive. View my complete profile.
naburnsludge.blogspot.com
NABURN WWTW SLUDGE MANAGEMENT SCHEME: Safe September
http://naburnsludge.blogspot.com/2007/10/post-9.html
NABURN WWTW SLUDGE MANAGEMENT SCHEME. Friday, 21 September 2007. In honour of behavioural safety week a workshop was run by the safety department, greeted with enthusiasm by all staff. The project is on programme and the testing including the FST5 air test has been carried out. The walkways and barriers have been reviewed and the review notes acted upon, as well as tool box talks on: machine buckets and protection to protruding rebar. Subscribe to: Post Comments (Atom). View my complete profile.
hullsludge.blogspot.com
HULL WWTW SLUDGE MANAGEMENT SCHEME: Current Activities
http://hullsludge.blogspot.com/2007/09/current-activities.html
HULL WWTW SLUDGE MANAGEMENT SCHEME. Friday, 28 September 2007. Subscribe to: Post Comments (Atom). Health and Safety Executive. View my complete profile. How often would you like to see this blog updated?
hullsludge.blogspot.com
HULL WWTW SLUDGE MANAGEMENT SCHEME: September 2007
http://hullsludge.blogspot.com/2007_09_01_archive.html
HULL WWTW SLUDGE MANAGEMENT SCHEME. Friday, 28 September 2007. Subscribe to: Posts (Atom). Health and Safety Executive. View my complete profile. How often would you like to see this blog updated?
naburnsludge.blogspot.com
NABURN WWTW SLUDGE MANAGEMENT SCHEME: April 2007
http://naburnsludge.blogspot.com/2007_04_01_archive.html
NABURN WWTW SLUDGE MANAGEMENT SCHEME. Sunday, 29 April 2007. Steel for the selector tank has been identified with most parts having already arrived for work to commence on 30-04-07. Wednesday, 25 April 2007. Excavations have been ongoing with an increase in staff numbers to speed up the works. Tool box talks have also had a focus with topics including:. Ladders and hand tools. The fencing has also been improved with the traffic management plan in place. Subscribe to: Posts (Atom). View my complete profile.