Monday, 4 March 2013. The deep drainage is now complete and the Hydro Brake cast in-situ manhole is ready to be concreted. The car parking bays have been formed and the block Pavia to this area completed. Also prepared are the cycle shed base and the bin store base. The boundary wall has been constructed just leaving the tango fencing to be fixed to it. Friday, 15 February 2013. Our first floor flats are ready to be handed over to the decorators, just got to fill the systems with water and check for leak...

http://wates-field-head.blogspot.com/

WEBSITE DETAILS
SEO
PAGES
SIMILAR SITES

TRAFFIC RANK FOR WATES-FIELD-HEAD.BLOGSPOT.COM

TODAY'S RATING

>1,000,000

TRAFFIC RANK - AVERAGE PER MONTH

BEST MONTH

February

AVERAGE PER DAY Of THE WEEK

HIGHEST TRAFFIC ON

Monday

TRAFFIC BY CITY

CUSTOMER REVIEWS

Average Rating: 4.1 out of 5 with 15 reviews
5 star
9
4 star
2
3 star
2
2 star
0
1 star
2

Hey there! Start your review of wates-field-head.blogspot.com

AVERAGE USER RATING

Write a Review

WEBSITE PREVIEW

Desktop Preview Tablet Preview Mobile Preview

LOAD TIME

0.9 seconds

FAVICON PREVIEW

  • wates-field-head.blogspot.com

    16x16

  • wates-field-head.blogspot.com

    32x32

  • wates-field-head.blogspot.com

    64x64

  • wates-field-head.blogspot.com

    128x128

CONTACTS AT WATES-FIELD-HEAD.BLOGSPOT.COM

Login

TO VIEW CONTACTS

Remove Contacts

FOR PRIVACY ISSUES

CONTENT

SCORE

6.2

PAGE TITLE
Field Head | wates-field-head.blogspot.com Reviews
<META>
DESCRIPTION
Monday, 4 March 2013. The deep drainage is now complete and the Hydro Brake cast in-situ manhole is ready to be concreted. The car parking bays have been formed and the block Pavia to this area completed. Also prepared are the cycle shed base and the bin store base. The boundary wall has been constructed just leaving the tango fencing to be fixed to it. Friday, 15 February 2013. Our first floor flats are ready to be handed over to the decorators, just got to fill the systems with water and check for leak...
<META>
KEYWORDS
1 posted by
2 wates team
3 no comments
4 email this
5 blogthis
6 share to twitter
7 share to facebook
8 share to pinterest
9 primary school
10 older posts
CONTENT
Page content here
KEYWORDS ON
PAGE
posted by,wates team,no comments,email this,blogthis,share to twitter,share to facebook,share to pinterest,primary school,older posts,or e mail,jodiewalker@wates co uk,blog archive,october
SERVER
GSE
CONTENT-TYPE
utf-8
GOOGLE PREVIEW

Field Head | wates-field-head.blogspot.com Reviews

https://wates-field-head.blogspot.com

Monday, 4 March 2013. The deep drainage is now complete and the Hydro Brake cast in-situ manhole is ready to be concreted. The car parking bays have been formed and the block Pavia to this area completed. Also prepared are the cycle shed base and the bin store base. The boundary wall has been constructed just leaving the tango fencing to be fixed to it. Friday, 15 February 2013. Our first floor flats are ready to be handed over to the decorators, just got to fill the systems with water and check for leak...

INTERNAL PAGES

wates-field-head.blogspot.com wates-field-head.blogspot.com
1

Field Head

http://www.wates-field-head.blogspot.com/2013/02/the-weather-has-definitely-been-on-our.html

Friday, 1 February 2013. The weather has definitely been on our side this week and we have been busy with our drainage both off-site and on-site. We have already made our connection onto the existing sewer for our discharge for the surface water and are busy constructing reinforced manholes and laying 525mm dia concrete pipes. We are getting very close for the first floor flats to be handed over to the decorators, just a final snag to go and then they can be given over to complete the flats.

2

Field Head: March 2013

http://www.wates-field-head.blogspot.com/2013_03_01_archive.html

Monday, 4 March 2013. The deep drainage is now complete and the Hydro Brake cast in-situ manhole is ready to be concreted. The car parking bays have been formed and the block Pavia to this area completed. Also prepared are the cycle shed base and the bin store base. The boundary wall has been constructed just leaving the tango fencing to be fixed to it. Subscribe to: Posts (Atom). Click above for more information on Wates Group Limited. Click above for more information on Kirklees Excellent Homes for Life.

3

Field Head

http://www.wates-field-head.blogspot.com/2013/03/the-deep-drainage-is-now-complete-and.html

Monday, 4 March 2013. The deep drainage is now complete and the Hydro Brake cast in-situ manhole is ready to be concreted. The car parking bays have been formed and the block Pavia to this area completed. Also prepared are the cycle shed base and the bin store base. The boundary wall has been constructed just leaving the tango fencing to be fixed to it. Note: only a member of this blog may post a comment. Subscribe to: Post Comments (Atom). Click above for more information on Wates Group Limited.

4

Field Head: September 2012

http://www.wates-field-head.blogspot.com/2012_09_01_archive.html

Wednesday, 19 September 2012. The brick work was complete to the underside of the floor last week, in preparation for the beam and block flooring contractor. Drainage elements have been laid by the groundworks contractor, and can be seen emerging from the foundations where they will be required for kitchens and bathrooms. Subscribe to: Posts (Atom). Click above for more information on Wates Group Limited. Click above for more information on Kirklees Excellent Homes for Life.

5

Field Head: October 2012

http://www.wates-field-head.blogspot.com/2012_10_01_archive.html

Friday, 26 October 2012. This week we all received the annual announcement to coincide with the start of the winter months that the average. Dual fuel bill would go up by 10.8%. Downing Street called the rise "very disappointing". This translates to the equivalent of more than £122 a year increase to an average annual fuel bill.unless you. Are fortunate enough to be moving into any of the new 'Kirklees Excellent Homes for Life'. The roofers also started to lay the slates. Friday, 19 October 2012. The sca...

UPGRADE TO PREMIUM TO VIEW 11 MORE

TOTAL PAGES IN THIS WEBSITE

16

OTHER SITES

waterzz.com waterzz.com

Waterzz

Find a wide selection of high quality bottled water for your home or business. Discover water coolers and accessories. We provide the widest range of water solutions from water coolers and water fountains. Start enjoying cleaner water today! We have top brands of water filters, from under sink to industrial grade. Flavored and Enhanced Water. Replacement Countertop Water Filters. Replacement Faucet Water Filters. Replacement Pitcher Water Filters. Replacement Under-Sink Water Filters. Filmtec TW30-1812-5...

wates-belle-vue-crescent.blogspot.com wates-belle-vue-crescent.blogspot.com

Belle Vue Crescent

Monday, 23 December 2013. The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Belle Vue Crescent. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January. Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year! Friday, 29 November 2013. Monday, 18 November 2013. External Finishes have now commenced with flagged paths and block paved drives.

wates-brown-royd-avenue.blogspot.com wates-brown-royd-avenue.blogspot.com

Brown Royd Avenue

Monday, 23 December 2013. The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Brown Royd Avenue. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January. Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year! Thursday, 7 November 2013. Friday, 25 October 2013. The base for the cycle store has been poured so that this area can be flagged.

wates-burgh-mill-gardens.blogspot.com wates-burgh-mill-gardens.blogspot.com

Burgh Mill Gardens

Monday, 22 April 2013. External groundworks are now underway with the installation of Drainage and Statutory services to the plots. Can we please ask all local residents to remind their children to not enter the site on a evenings and weekends. Thank you. Friday, 5 April 2013. Drainage works have progressed well this week, along with the commencement of the last two retaining walls which will then form the car park along the front of the flats. Wednesday, 13 March 2013. Monday, 4 March 2013. First fix bo...

wates-centenary-way.blogspot.com wates-centenary-way.blogspot.com

Centenary Way

Monday, 23 December 2013. The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Centenary Way. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January. Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year! Friday, 29 November 2013. Friday, 25 October 2013. Friday, 11 October 2013. Externally this week the bricklayers and renderers complete...

wates-field-head.blogspot.com wates-field-head.blogspot.com

Field Head

Monday, 4 March 2013. The deep drainage is now complete and the Hydro Brake cast in-situ manhole is ready to be concreted. The car parking bays have been formed and the block Pavia to this area completed. Also prepared are the cycle shed base and the bin store base. The boundary wall has been constructed just leaving the tango fencing to be fixed to it. Friday, 15 February 2013. Our first floor flats are ready to be handed over to the decorators, just got to fill the systems with water and check for leak...

wates-foldings-avenue.blogspot.com wates-foldings-avenue.blogspot.com

Foldings Avenue

Friday, 2 August 2013. Tuesday, 25 June 2013. Friday, 21 June 2013. We are only a few weeks from completion at Foldings Avenue, as you can see the internal finishes are 95% complete to both blocks, the external hard and soft landscaping is the current priority, however we a confident with a run of good weather this will be finished in the next week or so. Wednesday, 10 April 2013. Wednesday, 20 February 2013. Progress has been slow in January due to the adverse weather and cold temperatures, however Febr...

wates-former-fairfield-school.blogspot.com wates-former-fairfield-school.blogspot.com

Former Fairfield School

Thursday, 10 October 2013. We have come a long way since the blog has been down. With only weeks to go before handover the internal are almost complete. As you can see with the photos, the first and second floor are complete, only leaving the main entrance corridor to decorate. We are having the final push on the externals and the temporary car park being replaced back to the original state before we arrived. Monday, 22 July 2013. Friday, 5 July 2013. Friday, 21 June 2013. The second phase of External Wo...

wates-green-mount.blogspot.com wates-green-mount.blogspot.com

Green Mount

Tuesday, 6 August 2013. Mass concrete works have been completed to the retaining wall and the facing stonework has been laid ready for coping stones. Kerbing and hard landscaping works are progressing to the front of Block 1 and adjacent to Block 2. Friday, 21 June 2013. Excavations ,steel fixing and concrete pour for the retaining wall are now completed. The g. As trench is now excavated and g. As, water and electric are now connected to all plots. Monday, 22 April 2013. Monday, 8 April 2013. The stone ...

wates-hare-park-grange.blogspot.com wates-hare-park-grange.blogspot.com

Hare Park Grange

Friday, 8 February 2013. The project is now complete after a seamless handover to Kirklees council on Thursday 7th February. The project was completed to a high quality standard both internally and externally with complimentary remarks from the client and clients representative. Another excellent project delivered from the Wates Kirklees Team. A big thankyou to all involved. Tuesday, 5 February 2013. Internally, we have nearly completed the snagging list produced by Kirklees Council. After the Christmas ...